The time required for warehouse liquidation depends on the quantity and type of assets, the facility layout and the removal work involved. Collecting accessible surplus stock is different from dismantling storage systems and removing equipment throughout a building. Loading dock availability, permitted working hours and ongoing operations also affect the schedule.
For a 20,000–50,000 sq ft warehouse, on-site clearance typically takes 3–10 working days, including racking dismantling and removal. Smaller clearances without racking generally take 1–3 days.
Share your clearance deadline and identify anything that must remain in use until a particular date. MGT plans the dismantling, loading and transportation around those requirements. We also clarify how collection relates to any agreed resale arrangements, so you know when the space will be cleared and what work may continue afterwards.