The team removed more than 100 truckloads of furniture and contents using 26-foot trucks, while relocating selected assets. MGT coordinated electrical and data cabling work, server room decommissioning, HVAC work and fire stopping. The scope also included patching and painting, ensuring the project addressed both the removal of contents and the restoration of the space.
Eliminating unnecessary handling and storage
The building remained busy and occupied throughout the project, with all removals restricted to after 6 p.m. or weekends. MGT carefully scheduled truckloads and coordinated multiple trades around these restrictions, keeping work progressing across the floors. Managing the removal volume within limited access hours was the project’s biggest logistical challenge, which the team handled without major delays or issues.